What are the requirements for the pit construction of the lifting platform for aerial work

Time of publication:2020-08-10 10:16:43
What are the requirements for the pit construction of the lifting platform for aerial work

 What are the requirements for the pit construction of the lifting platform for aerial work

 
Hello, everyone, in the process of using the aerial work lifting platform, there are relatively high requirements for the pit building, because in the process of installation, it is considered that the use of the lifting platform is for the convenience of loading and unloading goods and can not affect the normal traffic. Then, how do we require the pit construction? The following is the specific description:
 
高空作业升降平台1.jpg
 
What are the requirements for the pit construction of the lifting platform for aerial work
 
The platform of the lifting platform should be level with the ground. At this time, the manufacturer of the lifting platform will issue the pit drawing. The user should build the pit in advance strictly according to the requirements of the drawing, and place the equipment in the pit during installation. The construction of high standard pit is the premise to ensure the high quality of lifting platform
 
1、 The pit ground shall be leveled with building cement during pouring, and the unevenness shall be less than 5mm. The pit depth (including embedded parts) shall be made according to the specific data provided by the lifting platform manufacturer, and the concrete thickness shall not be less than 15mm.
 
2、 The depth of the pit is consistent with the height of the lifting platform itself, and the length and width of the pit are about 10 cm more than those of the equipment. According to the specifications and models of the lifting platform, the manufacturer will provide different embedded parts. The purpose of reserving embedded iron parts is to weld the equipment and iron parts together to increase the reliability of the whole machine. If the pit construction is unreasonable and the elevator cannot be fixed horizontally, the center of gravity in the process of cargo security and lifting is skewed, and the equipment is subjected to uneven stress, which is easy to damage one side or part of the connecting parts and supporting rods of the machine, and the service life is naturally reduced.
 
3、 The diagonals of the pit mouth and bottom shall be equal, and the walls shall be perpendicular to each other and perpendicular to the pit bottom.
 
4、 The hole size of each floor shall be consistent with the pit size, and the four sides shall be perpendicular to each other.
 
5、 If the foundation is wet, moisture-proof treatment should be done. If there is water in the pit, drainage ditch should be made to prevent corrosion of the lifting platform.
 
In the actual construction process, there may be such and other problems, which requires timely communication with the technical personnel of the lifting platform manufacturer, and the construction can be carried out after the data are implemented, so as to avoid unnecessary losses.